December 2018

  • Installation of the Construction access platform/debris shield beneath the bridge
  • Removal of the concrete median barrier on the bridge
  • Diamond grinding of the median bridge deck
  • Removal of the gland from the longitudinal bridge deck joint
  • Removal of the concrete median roadway barriers off the bridge
  • Median paving
  • HMA S0.375 overlay of the right lane and the Exit 16 off-ramp on I-95 southbound
  • Pothole patching
  • All painted pavement markings on I-95 northbound and southbound were refreshed for improved visibility