January 2019 work activities included the following:
- Completed temporary transverse expansion joint treatments in the median
- Completed installation of bridge drain extension pipes
- Completed mark out for new IMS cable supports on Girder G-11
- Continued identification of concrete pier and abutment deficiencies
- Commenced with Class “S” Concrete and Variable Depth repairs
- Continued preparation of the bridge deck for the longitudinal expansion joint installation
- Commenced localized paint removal
- Commenced identification of structural steel deficiencies and steel repairs