February 2019 Update

February 2019 work activities included the following:

  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth repairs
  • Continued preparation of the bridge deck for the longitudinal expansion joint installation
  • Continued localized paint removal
  • Continued identification of structural steel deficiencies and steel repairs
  • Completed installation of new pavement markings on I-95 southbound across the bridge