April 2019 Update

April 2019 work activities included the following:

  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth repairs (swing staging installed on piers in the water)
  • Continued localized paint removal
  • Removed lead paint debris from the construction site
  • Continued identification of structural steel deficiencies and steel repairs
  • Continue identification of bottom side concrete deck deficiencies and repairs
  • Completed longitudinal and transverse bridge deck expansion joint installation
  • Completed temporary navigational light installation