- Continued identification of structural steel deficiencies and repairs
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Continued identification of concrete deck repairs
- Continued with partial depth and full depth concrete deck repairs (night)
- Commenced demolition of I-95 southbound, Stage 2 concrete parapet, curb and sidewalk
- Completed removal of I-95 southbound, Stage 2 metal bridge rail
- Completed tree trimming at the Exit 16 in-ramp to I-95 southbound
- Completed installation of I-95 southbound, Stage 2 temporary illumination
- Completed installation of erosion control and anti-tracking pad at the Hendricks Avenue commuter parking area