June 2019 Update

The following are the June 2019 work activities:

  • Continued localized paint removal
  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Completed installation of Stage 2 YDB sidewalk detour on the north side of the bridge and commenced Taxi service
  • Completed installation of Stage 2 temporary barrier on the north side of the bridge
  • Continued identification of concrete deck repairs
  • Continued with partial depth and full depth concrete deck repairs (night)
  • Continued patching of roadway potholes as required (night)