October 2019 Update

The following are the October 2019 work activities:

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Commenced with the West Street drainage repair work and bypass pump installation
  • Commenced demolition of existing pedestrian railing
  • Commenced preparation for new pedestrian rail post installation
  • Commenced installation of IMS conduit and supports onto Girder G-11