The following are the October 2019 work activities:
- Continued identification of structural steel deficiencies and repairs
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Commenced with the West Street drainage repair work and bypass pump installation
- Commenced demolition of existing pedestrian railing
- Commenced preparation for new pedestrian rail post installation
- Commenced installation of IMS conduit and supports onto Girder G-11