The following are the December 2019 work activities:
- Continued identification of structural steel deficiencies and repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Commenced haunch removal from top girder flanges over roadways and waterways
- Completed preparation and coating of reinforcing steel for the Stage 2 north parapet
- Commenced drilling and grouting of additional Stage 2 north parapet reinforcing steel
- Completed Stage 2 bridge deck preparation for new pedestrian rail post installation
- Completed Stage 2 partial depth bridge deck sidewalk repairs
- Completed Stage 2 bridge scupper bolt removal and replacement test location
- Continued with the West Street drainage repair work and bypass pump installation
- Completed installation of IMS conduit and supports onto Girder G-11
- Completed demolition of NE Pylon
- Completed placement of NE Pylon footing concrete
- Completed I-95 Southbound emergency bridge deck pothole repairs