December 2019 Update

The following are the December 2019 work activities:

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Commenced haunch removal from top girder flanges over roadways and waterways
  • Completed preparation and coating of reinforcing steel for the Stage 2 north parapet
  • Commenced drilling and grouting of additional Stage 2 north parapet reinforcing steel
  • Completed Stage 2 bridge deck preparation for new pedestrian rail post installation
  • Completed Stage 2 partial depth bridge deck sidewalk repairs
  • Completed Stage 2 bridge scupper bolt removal and replacement test location
  • Continued with the West Street drainage repair work and bypass pump installation
  • Completed installation of IMS conduit and supports onto Girder G-11
  • Completed demolition of NE Pylon
  • Completed placement of NE Pylon footing concrete
  • Completed I-95 Southbound emergency bridge deck pothole repairs