January 2019 Update

The following are the January 2019 work activities:

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Commenced haunch removal from top girder flanges over roadways and waterways
  • Completed drilling and grouting of additional Stage 2 north parapet reinforcing steel
  • Continued with the West Street drainage repair work and bypass pump installation
  • Commenced with the installation of electrical components in the Stage 2 Parapet including conduits and junction boxes
  • Commenced with the installation of Stage 2 Parapet Concrete form work
  • Commenced with the installation of Stage 2 Parapet reinforcing steel
  • Commenced with the placement of Stage 2 Parapet Concrete