- Continued identification of structural steel deficiencies and repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Completed haunch removal from top girder flanges over roadways and waterways
- Continued with the West Street drainage repair work and bypass pump installation
- Continued with the installation of electrical components in the Stage 2 Parapet including conduits and junction boxes
- Continued with the installation of Stage 2 Parapet Concrete form work
- Continued with the installation of Stage 2 Parapet reinforcing steel
- Continued with the placement of Stage 2 Parapet Concrete
- Completed installation of the IMS Conduit
- Completed the Girder G-11 web strengthening repair work
- Completed emergency repair of a hole in the bridge deck