February 2020 Update

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Completed haunch removal from top girder flanges over roadways and waterways
  • Continued with the West Street drainage repair work and bypass pump installation
  • Continued with the installation of electrical components in the Stage 2 Parapet including conduits and junction boxes
  • Continued with the installation of Stage 2 Parapet Concrete form work
  • Continued with the installation of Stage 2 Parapet reinforcing steel
  • Continued with the placement of Stage 2 Parapet Concrete
  • Completed installation of the IMS Conduit
  • Completed the Girder G-11 web strengthening repair work
  • Completed emergency repair of a hole in the bridge deck