The following are the January 2019 work activities:
- Continued identification of structural steel deficiencies and repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Commenced haunch removal from top girder flanges over roadways and waterways
- Completed drilling and grouting of additional Stage 2 north parapet reinforcing steel
- Continued with the West Street drainage repair work and bypass pump installation
- Commenced with the installation of electrical components in the Stage 2 Parapet including conduits and junction boxes
- Commenced with the installation of Stage 2 Parapet Concrete form work
- Commenced with the installation of Stage 2 Parapet reinforcing steel
- Commenced with the placement of Stage 2 Parapet Concrete