March 2019 work activities included the following:
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth repairs
- Continued preparation of the bridge deck for the longitudinal expansion joint installation
- Continued localized paint removal
- Continued identification of structural steel deficiencies and steel repairs
- Continue identification of bottom side concrete deck deficiencies and repairs
- Completed installation of bird deterrent netting