April 2019 work activities included the following:
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth repairs (swing staging installed on piers in the water)
- Continued localized paint removal
- Removed lead paint debris from the construction site
- Continued identification of structural steel deficiencies and steel repairs
- Continue identification of bottom side concrete deck deficiencies and repairs
- Completed longitudinal and transverse bridge deck expansion joint installation
- Completed temporary navigational light installation