February 2020 Update

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Completed haunch removal from top girder flanges over roadways and waterways
  • Continued with the West Street drainage repair work and bypass pump installation
  • Continued with the installation of electrical components in the Stage 2 Parapet including conduits and junction boxes
  • Continued with the installation of Stage 2 Parapet Concrete form work
  • Continued with the installation of Stage 2 Parapet reinforcing steel
  • Continued with the placement of Stage 2 Parapet Concrete
  • Completed installation of the IMS Conduit
  • Completed the Girder G-11 web strengthening repair work
  • Completed emergency repair of a hole in the bridge deck

January 2019 Update

The following are the January 2019 work activities:

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Commenced haunch removal from top girder flanges over roadways and waterways
  • Completed drilling and grouting of additional Stage 2 north parapet reinforcing steel
  • Continued with the West Street drainage repair work and bypass pump installation
  • Commenced with the installation of electrical components in the Stage 2 Parapet including conduits and junction boxes
  • Commenced with the installation of Stage 2 Parapet Concrete form work
  • Commenced with the installation of Stage 2 Parapet reinforcing steel
  • Commenced with the placement of Stage 2 Parapet Concrete

December 2019 Update

The following are the December 2019 work activities:

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Commenced haunch removal from top girder flanges over roadways and waterways
  • Completed preparation and coating of reinforcing steel for the Stage 2 north parapet
  • Commenced drilling and grouting of additional Stage 2 north parapet reinforcing steel
  • Completed Stage 2 bridge deck preparation for new pedestrian rail post installation
  • Completed Stage 2 partial depth bridge deck sidewalk repairs
  • Completed Stage 2 bridge scupper bolt removal and replacement test location
  • Continued with the West Street drainage repair work and bypass pump installation
  • Completed installation of IMS conduit and supports onto Girder G-11
  • Completed demolition of NE Pylon
  • Completed placement of NE Pylon footing concrete
  • Completed I-95 Southbound emergency bridge deck pothole repairs

 

November 2019 Update

The following are the November 2019 work activities:

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Continued with the West Street drainage repair work and bypass pump installation
  • Completed demolition of existing pedestrian railing
  • Continued preparation for new pedestrian rail post installation
  • Continued installation of IMS conduit and supports onto Girder G-11
  • Commenced preparation and coating of reinforcing steel for the north parapet
  • Commenced demolition of NE Pylon

 

 

October 2019 Update

The following are the October 2019 work activities:

  • Continued identification of structural steel deficiencies and repairs
  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
  • Continued identification of bottom side concrete deck deficiencies and repairs
  • Commenced with the West Street drainage repair work and bypass pump installation
  • Commenced demolition of existing pedestrian railing
  • Commenced preparation for new pedestrian rail post installation
  • Commenced installation of IMS conduit and supports onto Girder G-11