Author: Juan Lopez
April 2019 Update
April 2019 work activities included the following:
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth repairs (swing staging installed on piers in the water)
- Continued localized paint removal
- Removed lead paint debris from the construction site
- Continued identification of structural steel deficiencies and steel repairs
- Continue identification of bottom side concrete deck deficiencies and repairs
- Completed longitudinal and transverse bridge deck expansion joint installation
- Completed temporary navigational light installation
March 2019 Update
March 2019 work activities included the following:
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth repairs
- Continued preparation of the bridge deck for the longitudinal expansion joint installation
- Continued localized paint removal
- Continued identification of structural steel deficiencies and steel repairs
- Continue identification of bottom side concrete deck deficiencies and repairs
- Completed installation of bird deterrent netting
March 2019 Photos
February 2019 Update
February 2019 work activities included the following:
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth repairs
- Continued preparation of the bridge deck for the longitudinal expansion joint installation
- Continued localized paint removal
- Continued identification of structural steel deficiencies and steel repairs
- Completed installation of new pavement markings on I-95 southbound across the bridge
February 2019 Photos
January 2019 Update
January 2019 work activities included the following:
- Completed temporary transverse expansion joint treatments in the median
- Completed installation of bridge drain extension pipes
- Completed mark out for new IMS cable supports on Girder G-11
- Continued identification of concrete pier and abutment deficiencies
- Commenced with Class “S” Concrete and Variable Depth repairs
- Continued preparation of the bridge deck for the longitudinal expansion joint installation
- Commenced localized paint removal
- Commenced identification of structural steel deficiencies and steel repairs
January 2019 Photos
December 2018
December 2018
- Installation of the Construction access platform/debris shield beneath the bridge
- Removal of the concrete median barrier on the bridge
- Diamond grinding of the median bridge deck
- Removal of the gland from the longitudinal bridge deck joint
- Removal of the concrete median roadway barriers off the bridge
- Median paving
- HMA S0.375 overlay of the right lane and the Exit 16 off-ramp on I-95 southbound
- Pothole patching
- All painted pavement markings on I-95 northbound and southbound were refreshed for improved visibility