April 2019 Update

April 2019 work activities included the following:

  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth repairs (swing staging installed on piers in the water)
  • Continued localized paint removal
  • Removed lead paint debris from the construction site
  • Continued identification of structural steel deficiencies and steel repairs
  • Continue identification of bottom side concrete deck deficiencies and repairs
  • Completed longitudinal and transverse bridge deck expansion joint installation
  • Completed temporary navigational light installation

March 2019 Update

March 2019 work activities included the following:

  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth repairs
  • Continued preparation of the bridge deck for the longitudinal expansion joint installation
  • Continued localized paint removal
  • Continued identification of structural steel deficiencies and steel repairs
  • Continue identification of bottom side concrete deck deficiencies and repairs
  • Completed installation of bird deterrent netting

February 2019 Update

February 2019 work activities included the following:

  • Continued identification of concrete pier and abutment deficiencies
  • Continued with Class “S” Concrete and Variable Depth repairs
  • Continued preparation of the bridge deck for the longitudinal expansion joint installation
  • Continued localized paint removal
  • Continued identification of structural steel deficiencies and steel repairs
  • Completed installation of new pavement markings on I-95 southbound across the bridge

January 2019 Update

January 2019 work activities included the following:

  • Completed temporary transverse expansion joint treatments in the median
  • Completed installation of bridge drain extension pipes
  • Completed mark out for new IMS cable supports on Girder G-11
  • Continued identification of concrete pier and abutment deficiencies
  • Commenced with Class “S” Concrete and Variable Depth repairs
  • Continued preparation of the bridge deck for the longitudinal expansion joint installation
  • Commenced localized paint removal
  • Commenced identification of structural steel deficiencies and steel repairs

January 2019 Photos

December 2018

  • Installation of the Construction access platform/debris shield beneath the bridge
  • Removal of the concrete median barrier on the bridge
  • Diamond grinding of the median bridge deck
  • Removal of the gland from the longitudinal bridge deck joint
  • Removal of the concrete median roadway barriers off the bridge
  • Median paving
  • HMA S0.375 overlay of the right lane and the Exit 16 off-ramp on I-95 southbound
  • Pothole patching
  • All painted pavement markings on I-95 northbound and southbound were refreshed for improved visibility