November 2018

In November assembly of the construction access platform beneath the bridge continued. Once completed this platform will not only be used by the contractors as a debris shield, but it will also be used to access many future work activities including:

  • Repair and painting of existing structural steel
  • Ultrasonic impact strengthening and repair of existing welds
  • Underside bridge deck concrete repairs
  • Concrete pier and abutment repairs
  • Bridge drainage system replacement including fiberglass pipes and scupper hoppers
  • Replacement of the existing Incident Management System (IMS) conduit and cable
  • Replacement of the existing navigational lighting system
  • Installation of an Avian Nesting Box for the Peregrine Falcons

Work on the I-95 Roadway at night continued including the following work activities:

  • Removal of the existing median barrier on and off the bridge
  • Cleaning of scuppers on the bridge and catch basins in the roadway for improved drainage
  • Patching of deteriorated bridge deck areas and roadway potholes
  • Modification of the median bridge expansion joints

Anticipated December work activities include the following:

  • Construction access platform completion
  • Diamond grinding the median bridge deck
  • Complete cleaning of scuppers on the bridge and catch basins in the roadway for improved drainage
  • Complete removal of the concrete median roadway barriers off the bridge and pave the void
  • Complete patching of deteriorated bridge deck areas
    Continue patching of potholes as required
  • Complete bridge median expansion joint modifications
  • Shift I-95 SB traffic to the south to create a work zone on the north side of the bridge that will allow modifications to the existing parapets and sidewalk.