Category: Updates
September 2019 Update
The following are the September 2019 work activities:
- Continued identification of structural steel deficiencies and repairs
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Completed demolition of I-95 southbound, Stage 2 concrete parapet, curb and sidewalk
- Completed demolition of I-95 southbound, Stage 2 concrete sidewalk expansion joints
- Completed navigation light service panel repairs
- Build I-95 southbound, Stage 2 wooden pylon forms
August 2019 Update
The following are the August 2019 work activities:
- Continued identification of structural steel deficiencies and repairs
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Continued demolition of I-95 southbound, Stage 2 concrete parapet, curb and sidewalk
July 2019 Photos
July 2019 Update
- Continued identification of structural steel deficiencies and repairs
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Continued identification of concrete deck repairs
- Continued with partial depth and full depth concrete deck repairs (night)
- Commenced demolition of I-95 southbound, Stage 2 concrete parapet, curb and sidewalk
- Completed removal of I-95 southbound, Stage 2 metal bridge rail
- Completed tree trimming at the Exit 16 in-ramp to I-95 southbound
- Completed installation of I-95 southbound, Stage 2 temporary illumination
- Completed installation of erosion control and anti-tracking pad at the Hendricks Avenue commuter parking area
June 2019 Update
The following are the June 2019 work activities:
- Continued localized paint removal
- Continued identification of structural steel deficiencies and repairs
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth pier and abutment repairs
- Continued identification of bottom side concrete deck deficiencies and repairs
- Completed installation of Stage 2 YDB sidewalk detour on the north side of the bridge and commenced Taxi service
- Completed installation of Stage 2 temporary barrier on the north side of the bridge
- Continued identification of concrete deck repairs
- Continued with partial depth and full depth concrete deck repairs (night)
- Continued patching of roadway potholes as required (night)
June 2019 Photos
May 2019 Update
May 2019 work activities included the following:
- Continued identification of concrete pier and abutment deficiencies
- Continued with Class “S” Concrete and Variable Depth repairs
- Continued localized paint removal (Spans 2 & 3)
- Continued identification of structural steel deficiencies and steel repairs (Spans 1 & 2)
- Continue identification of bottom side concrete deck deficiencies and repairs
- MBI 2019 night work commenced on Tuesday May 14th
- Refreshed I-95 Southbound painted pavement markings (night)
- Continued identification of concrete deck repairs (night)
- Commenced with partial depth concrete deck repairs (night)
- Commenced installation of strip drains east of the bridge in the I-95 median (night)